Wind Energy – Fecamp France
On July 31, Heerema Marine Contractors’ Sleipnir reached EDF’s Fécamp wind farm offshore France, to install 71 concrete gravity-based foundations.
[Read more…] about First foundation installation campaign for SleipnirGLOBAL NEWS SERVICE FOR THE FOSSIL AND RENEWABLE ENERGY COMMUNITIES
On July 31, Heerema Marine Contractors’ Sleipnir reached EDF’s Fécamp wind farm offshore France, to install 71 concrete gravity-based foundations.
[Read more…] about First foundation installation campaign for Sleipnir
TAQA announced it has completed the safe and successful removal of the Brae Alpha West drilling rig and the Brae Bravo upper main jacket in the Northern North Sea.
[Read more…] about Large-scale offshore decom project in Brae Field completed
Heerema’s Sleipnir has successfully delivered Fairfield Energy Limited’s huge Dunlin Platform topsides for recycling and reuse!
[Read more…] about Dunlin platform topsides delivered
On behalf of client Fairfield Energy, Heerema Marine Contractors will soon be removing several smaller modules followed by the platform’s massive module support frame with a single lift.
[Read more…] about Heerema to kick off Dunlin decommissioning
Heerema Marine Contractors is set to start the decommissioning of the Dunlin Alpha platform for Fairfield Energy.
[Read more…] about Heerema gears up for Dunlin Alpha decommissioning
With new topsides and bridges, Total is one step closer to completing the Tyra Redevelopment Project.
[Read more…] about New topsides and bridges for Tyra (VIDEO)
Heerema Marine Contractors has been appointed INPEX’s contractor of choice for the transport and installation of the 4,800 metric ton Ichthys LNG Booster Compression Module (BCM).
[Read more…] about HMC awarded Ichthys LNG transport and installation contract
Recently Heerema’s Sleipnir and its crew were back again at the Tyra Field to install three topsides for TotalEnergies.
[Read more…] about Sleipner installed three Tyra topsides (VIDEO)
According to Morten Hesselager Pedersen, Vice President, Head of the Tyra Redevelopment at TotalEnergies, crane vessel Sleipnir has lifted and installed the first new topside for the Tyra redevelopment in the Danish North Sea.
[Read more…] about Heerema’s Sleipnir installs first Tyra topsides
On June 18, Heerema’s Sleipnir successfully installed the 12,050 metric ton Johan Sverdrup processing platform (P2) jacket, setting a new record for the heaviest lift jacket installation.
[Read more…] about Sleipnir breaks records on Johan Sverdrup Phase 2 development project