Fossil Energy – Tyra II
Heerema’s Sleipnir successfully installed the final Tyra II structures this weekend!
On behalf of TotalEnergies and Danish Underground Consortium Partners, Heerema Marine Contractors installed two bridges and a flare tower.
Both bridges were over 85-meters, and were installed using both cranes in a dual-crane lift
The installed flare tower is 170-meters above sea level.
Now that all eight platforms, six bridges, two jackets, and the flare are in position, and after the Heerema team finished the completion activities, the company concluded its scope on Tyra II!