Hollandse Kust (zuid) Sea Cables project is part of the ‘Net on zee’ programme of TenneT.
This offshore project connects the Hollandse Kust (zuid) offshore wind farms to the onshore high voltage grid.
The connection is split up into Alpha and Beta, each of which contains a capacity of 700 megawatt power.
A consortium is formed by Van Oord and Hellenic Cables for the purpose of designing, producing, transporting and installing the required 168 km of high voltage cables.