Another major move for OSS Zingst and Darß

Tuesday, September 22 2026

OSS

Following the jackets, the topsides for the two offshore substations (OSS) have now completed their load-outs.

The OSS Zingst topside was loaded out in Schiedam, while the OSS Darß topside was loaded out in Vlissingen. Each topside has a capacity of approximately 450 MW.

OSS Zingst and OSS Darß are part of 50Hertz Transmission GmbH’s OST-6-1 grid connection for the 927 MW Gennaker Offshore Wind Farm.

Through the HSI Joint Venture, Smulders HSM and Iv are responsible for the complete EPCIC scope for the topsides and jackets of both offshore substations.

With the load-outs completed, the project is approaching its next defining milestone: sail-away.

Related posts:

  1. HSI awarded EPCI platform contract for wind farm in Baltic Sea
  2. First Load-Out CWP for Hornsea 3 completed
  3. Smulders HSM awarded contract next phase N05-A development
  4. OEG secures subsea corrosion protection contract for Gennaker OWF

Filed Under: Gennaker, International News, Load-out, OSS, Smulders HSM Tagged With: Darß, Gennaker, load out, offshore substations, Smulders HSM, Zingst

All rights reserved - 2026 cookies