Construction He Dreiht partially suspended due to detached Vestas blade

Tuesday, August 11 2026

Detached Blade

Work at EnBW’s 960MW He Dreiht offshore wind farm in the German part of the North Sea has been partially suspended due to a detached Vestas blade.

The blade broke loose from one of the turbines in late July.

During EnBW’s analyst call last Friday, Deputy CEO and CFO Thomas Kusterer said that ‘certain activities have been temporarily paused as a precaution’.

EnBW is currently prohibited from carrying out work on the affected turbine or blades from the same production site. However, Kustere emphasised that the basic commissioning of the wind farm is progressing well and continues.

The 960 MW project comprises 64 of Vestas’ flagship 15 MW V236 turbines. Last year, He Dreiht became the first project to successfully commission a V236 turbine.

Related posts:

  1. Vestas secures order for EnBW’s He Dreiht offshore wind project
  2. EnBW lays first submarine cable for He Dreiht OWF
  3. First wind turbine of ‘EnBW He Dreiht’ is up!
  4. Long-term purchase agreement for power supply He Dreiht OWF

Filed Under: blade, blade factory, EnWB, He Dreiht, International projects, Vestas Tagged With: Blade, construction, EnBW, He Dreiht, suspended, Vestas

All rights reserved - 2026 cookies