Van Oord has completed the transport and installation of 21 monopiles at Iberdrola’s Windanker OWF in the German Baltic Sea.

Sustainable choices played a defining role in the design and execution of this project.
The monopiles include some of the largest Van Oord ever installed.
Joost van Wiechen, Project Manager at Van Oord: “Completing the transport and installation of all monopiles at the Windanker offshore wind farm marks an important milestone for the project. This achievement reflects the dedication and expertise of our teams, the excellent collaboration with our client Iberdrola, and the outstanding performance of the Svanen. We are proud to have installed our largest and heaviest monopile to date, which demonstrates our commitment to enhancing the energy transition and delivering sustainable solutions for the future.”
Once operational, Windanker will add 315 MW of renewable energy, enough to power 315,000 households, to Iberdrola’s Baltic Hub.