DEA opens tenders for three new Danish offshore wind farms

Friday, November 21 2025

Wind Energy – Denmark

The Danish Energy Agency (DEA) issued tenders for three areas to develop at least 2.8 GW of offshore wind power.

Illustration: The Danish Energy Agency.

The areas are North Sea Mid, Hesselø in the Kattegat, and North Sea South. The tenders are based on thorough market dialogues and include state subsidies and greater flexibility for developers to increase the likelihood of qualified bids.

In total, the wind power farms will be able to supply green electricity equivalent to the consumption of around three million Danish and European homes.

The three offshore wind farms are being offered with a support scheme known as a 2-sided capability-based contract for difference (CfD). Under this scheme, the state guarantees offshore wind producers a fixed price for their electricity.

This reduces the risk of low electricity prices for developers – an element that has been requested by the market. In total a payment cap of DKK 55.2 billion including VAT has been set for the state.

The tenders contain requirements relating to sustainability and social responsibility, including requirements concerning the recyclability of the turbine blades, requirements against social dumping, and the winning bidder for Hesselø must establish the offshore wind farm with a so-called nature-inclusive design.

The tenders are a follow-up to the offshore wind tenders from 2024, where six areas were put up for tender. By the end of the deadline for the first three areas, the Danish Energy Agency had not received any bids. Subsequently, the Danish Energy Agency has held several market dialogues, which formed the basis for two political agreements in 2025. The new 2.8 GW offshore wind tenders are based on these agreements.

Facts about the three offshore wind areas:

– North Sea Mid, minimum 1 GW, must be completed by the end of 2032.

– Hesselø in the Kattegat, minimum 800 MW, must be completed by the end of 2032.

– North Sea South, minimum 1 GW, must be completed by the end of 2034.

Related posts:

  1. Denmark to launch North Sea Energy Island tender spring 2023
  2. The Danish Energy Agency has not received any bids
  3. Denmark awards first CO2 storage licences in North Sea
  4. Shell joins VindØ consortium to build Denmark’s first energy island

Filed Under: Denmark, International News, Tenders Tagged With: Denmark, tenders

All rights reserved - 2025 cookies