Ningbo Orient Wires & Cables from China completed the installation and trenching of 35,2 km of 220kV export cable within three days for the Longyuan SY wind farm.
On July 18, when the last meter on the carousel sank into the sea, the laying in deep water came to an end. The project ended with the near shore cable landing.