FID
TotalEnergies has taken the Final Investment Decision to develop the offshore Ima gas field in Nigeria.

Located near Bonny Island, the development comprises an offshore platform connected to the Nigeria LNG facility via a 22-kilometre pipeline.
Production is scheduled to commence in 2028, reaching a plateau of 350 million cubic feet of gas per day (over 60,000 boe/d).
The offshore platform EPCC contract has been awarded to Aveon Offshore and 2H Offshore, reflecting a strong commitment to Nigerian content.
The project is expected to supply approximately one-third of the gas required for Nigeria LNG’s Train 7 expansion, increasing liquefaction capacity from 22 to 30 million tonnes per annum.
With its lower-emissions design and significant local workforce participation, Ima represents a strategic investment in Nigeria’s gas infrastructure, industrial development and long-term global LNG competitiveness.