Adura
On 16 November 2026, Adura announced first gas from the Jackdaw field in the central North Sea, 26 days after the NSTA reconsented field development.

Gas flows through a 31 km tieback to the Shearwater hub and then on to the St Fergus gas terminal.
Adura expects output to peak at about 40,000 boe/d in the coming months.
The ultra-HPHT gas-condensate field was discovered in 2005 and Shell took FID in July 2022. A 2025 Court of Session ruling quashed the original consent over end-use emissions.
Drilling and construction continued through the reapplication, meaning the field was ready to start production on approval.
Attention now turns to Rosebank, Adura’s larger West of Shetland development, which still awaits a government decision.