Van Oord and Vestas install last turbine at Ecowende

Monday, November 2 2026

Wind Energy

The last of the 52 wind turbines at the Ecowende offshore wind farm was installed on October 30th, 2026.

The turbine stands approximately 53 kilometres off the coast of IJmuiden, in the Hollandse Kust (west) wind farm zone, Lot VI. With this milestone, Ecowende enters the final phase of construction. The wind farm is expected to be operational by the end of 2026.

The first turbine was installed on 30 May of this year, meaning all 52 turbines were installed in less than five months.

Vestas supplies the V236-15.0 MW turbines and is responsible for their installation and commissioning. Van Oord transports the turbines from Eemshaven to the offshore site using its installation vessel Boreas.

Van Oord previously installed the foundations and the inter-array cables.

Related posts:

  1. Turbine installation for Ecowende’s HKW gets underway
  2. Industry first completion of silent monopile installations
  3. Van Oord USV completes offshore debut
  4. Van Oord completes eco-scour protection installation HKW wind farm

Filed Under: Ecowende, International News, turbine installation, Van Oord, Vestas Tagged With: Ecowende, turbine instalation, Van Oord, Vestas

All rights reserved - 2026 cookies