New platform for Perenco on B14 Tchatamba field

Thursday, October 8 2026

Gabon

Last week, Dixstone, an affiliate of the Perenco Group, completed the lifting, upending, and final positioning of a new jacket structure for Perenco.

Completed with its own assets at 50m water depth, the operation required extensive preparation and a creative approach, resulting in an operation that ran to plan.

The coming weeks will entail piling work, followed by installing the topside structures fabricated in Gabon.

Related posts:

  1. SFE installs first jacket at 300MW offshore wind farm
  2. Topside for transformer platform departs for installation
  3. Saipem completes installation production platform Neptun Deep
  4. New platform installed offshore Norway for future energy production

Filed Under: Gabon, Installation, International News, Jacket, Perenco Tagged With: Dixstone, Gabon, Installation, jacket, Perenco, Tchatamba field

All rights reserved - 2026 cookies