Heerema Marine Contractors has completed the offshore foundation installation campaign for the Bałtyk 2 and Bałtyk 3 offshore wind farms in the Baltic Sea.

Working for the Equinor-Polenergia joint venture, Heerema installed the foundations for 100 wind turbines and two offshore substations over a four-month offshore campaign.
Using the semi-submersible crane vessel Thialf, and a fleet of approximately 35 support vessels, Heerema safely installed 100 monopiles, 100 transition pieces and two offshore substation jackets.