Milestone for DEME
DEME reached a major milestone at the Dieppe–Le Tréport offshore wind farm.

Less than a year after the first jacket foundation was installed in September 2025, all 62 jacket foundations are now in place.
Installed by the jack-up offshore installation vessel Innovation, the campaign involved 32 rotations between the port of Cherbourg and the offshore site, emphasizing the scale of the logistics and coordination behind a project of this size.
The jackets were installed on the 248 pin piles previously installed by our jack-up offshore installation vessel Apollo.