Wind Energy
Iberdrola has completed the inter-array cable installation campaign for its Windanker offshore wind farm in the German Baltic Sea.

The campaign was carried out by Van Oord and involved the installation of 21 inter-array cables, with 28 km of cable laid and buried.
The Windanker offshore wind farm is located about 45 km northeast of the island of Rügen and will add 315 MW of generation capacity to Iberdrola’s Baltic Hub.
The project will feature 21 Siemens Gamesa 15 MW wind turbines to be installed by DEME’s Norse Energi.
Windanker is scheduled to be fully commissioned in 2027.