Wind Energy – Gennaker
Skyborn Renewables has signed a contract with Dajin Heavy Industry for the supply of transition pieces for the Gennaker offshore wind farm in Germany.

This follows the preferred supply agreement (PSA) that the two companies signed in September 2025.
At that time, Skyborn also signed PSAs for foundations with EEW Special Pipe Construction (EEW SPC) and for transportation and installation services with Seaway7. Additionally, they signed an agreement with a Boskalis–TKF consortium for the supply and installation of inter-array cables.
The 64 monopiles will be manufactured in Rostock in north-east Germany. Each foundation will weigh up to 877 tonnes and have a top diameter of 7.5 metres.
With an installed capacity of up to 976.5 MW, the Gennaker project is located in the German Baltic Sea and is scheduled for commissioning in 2028. It will supply clean electricity to around one million households.