Wind Energy – Concrete Working Platform
On 20 October 2025, the Aarsleff Biz team in Świnoujście, Poland, successfully carried out the first of 21 planned load-outs of Concrete Working Platforms (CWPs) for the Hornsea 3 offshore wind farm.

This milestone marks the start of a new phase in deliveries – operations will continue until September 2026, covering the transport of 197 fully outfitted platforms and MP doors.
Following the successful load-out, the vessel is now sailing to the Port of Tyne (UK), where a foundation mock-up will take place – an important preparatory step ahead of future installation campaigns.