First Load-Out CWP for Hornsea 3 completed

Wednesday, November 5 2025

Wind Energy – Concrete Working Platform

On 20 October 2025, the Aarsleff Biz team in Świnoujście, Poland, successfully carried out the first of 21 planned load-outs of Concrete Working Platforms (CWPs) for the Hornsea 3 offshore wind farm.

This milestone marks the start of a new phase in deliveries – operations will continue until September 2026, covering the transport of 197 fully outfitted platforms and MP doors.

Following the successful load-out, the vessel is now sailing to the Port of Tyne (UK), where a foundation mock-up will take place – an important preparatory step ahead of future installation campaigns.

Related posts:

  1. Load out of THOR jacket in Schiedam
  2. Load out THOR OHVS substation
  3. Cadeler and Boston Energy announce partnership on Hornsea 3
  4. Second Hornsea 3 substation topside en route to Europe

Filed Under: Aarsleff, CWP, Hornsea 3, International News, Load-out Tagged With: Aarsleff BIZ, CWP, Hornsea 3, load out

All rights reserved - 2025 cookies