First energization of offshore station BorWin5

Wednesday, September 3 2025

Wind Energy – BorWin5

The BorWin5 project is progressing stroke on stroke.

Only three weeks after first energization of the onshore station Siemens Energy energized  also the offshore converter for the first time.

Considering that first access to the platform in the offshore location was possible only two and a half months ago this is an even more remarkable achievement.

Already in September the BorWin5 link will transmit first renewable power from EnBW’s offshore wind farm HeDreiht to the German onshore grid.

Siemen sEnergy with its consortium partner Dragados Offshore is constructing BorWin5 for TenneT as one element of the German energy transition.

Related posts:

  1. Converter station BorWin5 departed from Dragados
  2. Yellow giant has safely arrived in Haugesund
  3. DolWin epsilon installed in North Sea
  4. Siemens Energy named as preferred bidder for EGL4 project

Filed Under: Borwin5, Converter platform, energization, International News, renewable-powered platform, Siemens Energy, Tennet Tagged With: BorWin5, converter, energization, renewable power, Siemens Energy, tennet