Wind Energy – Cable Installation
Taihan Cable & Solution’s cable-laying vessel (CLV), PALOS, has completed the installation of export cables for the Yeonggwang Nakwol offshore wind project.

The project, located near Songido, Nakwol-myeon, Yeonggwang-gun, Jeollanam-do, is a large-scale initiative to develop a 364.8 MW wind power complex.
With a total project cost of KRW 2.3 trillion, the facility will generate enough electricity to power approximately 250,000 households year-round upon completion. The overall project progress has now surpassed 50%.
This project marks the first deployment of PALOS since its acquisition by Taihan. The export cable installation, covering two 28 km lines, was carried out in two phases: the first phase took place over two weeks in mid-May, and the second phase began in late June and was completed week commencing 7 July 2025.
The installation of inter-array cables, also produced by Taihan, is scheduled to commence after July.