Wind Energy – Cajuina Wind Complex
Brazil-based energy holding company Auren Energia has commissioned the Nordex Group to supply and install 19 N163/5.X turbines.
The 112 MW order includes the service for the turbines for an initial period of fifteen years, with several options to extend up to 30 years.
The turbines are destined for the Cajuína 3 wind farm which is part of the Cajuína Wind Complex in the state of Rio Grande do Norte in the municipality of Lajes.
The 19 turbines are due to be installed beginning of 2026 and will be supplied in an operating mode of 5.9 MW on 120-meter concrete towers. Commissioning is scheduled for autumn 2026.