Wind Energy – Greater Changhua
In a post on LinkedIn Jayaram Naidu, Vice President and Managing Director Greater Changhua shared the news that the offshore substation (OSS) of the Greater Changhua 2b and 4 offshore wind farms has set sail from Singapore.

The OSS is on its way to Port of Taichung. The jacket has already arrived, and the topside has sailed away yesterday on Feb 12.
The structural work of the 3,260-ton topside and the 3,137-ton OSS jacket foundations was completed in just 212 days, setting a new Ørsted record.