Wind Energy – Cable Installation
Axess Technologies has been awarded a contract by Hellenic Cables for cable installation work on the Ostwind 3 project in the German Baltic Sea.
The project scope includes planning and installing 66 kV and 220 kV internal platform cables for the offshore high-voltage substation. Engineering is already underway, with execution set to begin in Q2 2025 at HSM’s Stormpolder Yard in the Netherlands.
“This project is fully aligned with our strategy to become a turnkey supplier for HV cable pull-ins, terminations, and testing within the wind industry,” said Erik Wold Aalde, Director of Renewables at Axess Technologies.
Ostwind 3 will connect the Windanker wind farm area to Germany’s extra-high voltage grid.
Expected to be completed in 2026, the project will supply 300 MW of green energy, powering approximately 260,000 households.