Nexans has been awarded a substantial contract by Svenska kraftnät to deliver 320 km of high-voltage subsea and onshore cables for the Gotland Connection project in Sweden.
The project will address growing electricity demand on Gotland, ensuring a reliable energy supply for the island.
Scheduled for completion by mid-2030, the project will play a key role in supporting Sweden’s renewable energy transition goals.
The Gotland Connection will strengthen the electricity supply between Gotland and mainland Sweden. The installation of 320 km of 220 kV HVAC, subsea and onshore cables, will help meet the growing demand for electricity caused by industrial growth and renewable energy projects on the island.
Under this contract, Nexans will supply and install high-quality cable systems, which will be manufactured at several of the company’s plants. These cables are designed for reliable performance and future use in renewable energy applications.