Wind Energy – Yunlin Taiwan
Jumbo Offshore has completed its TP (transition piece) T&I (transport & installation scope) on the Yunlin Offshore Wind Farm (OWF) in Taiwan under a contract with Yunneng Wind Power.
For its role on the project, Jumbo Offshore deployed its DP2 Heavy Lift Crane Vessel Jumbo Javelin.
Prior to undertaking the project, Jumbo Offshore carried out extensive project preparations to ensure a smooth, reliable project execution.
Following this, Jumbo Javelin was outfitted in a project-specific set-up. This included the Jumbo Fly-Jib modular crane boom extension. This feature can be mounted on a Jumbo J-Class vessel to increase the lifting height. With this, the vessel was provided with the capability to lift the 27 m high TPs.
Jumbo Javelin performed the final TP installation on Friday, August 23. The vessel was loaded out with TPs in Kaohsiung, transporting up to four 450t TPs at one time. In total, Jumbo Javelin transported and installed 80 TPs during the project.
Water depths at the Yunlin OWF vary between 7 and 35m. The shallower water location are not suitable for installation in DP mode. Therefore, Jumbo Offshore switched between installation on DP and installation on anchors, making full use of the vessel’s versatility.
The Yunlin OWF is located in the Taiwan Strait, between 8 and 17 km from the coast of Taiwan.