Wind Energy – Monopiles
Sif Holding confirms the signing of the final contracts for the supply of 100 monopiles to the joint venture of Equinor and Polenergia for the Bałtyk II + Bałtyk III offshore wind projects.
Manufacturing of the monopiles is scheduled to begin in the second quarter of 2025 with completion in the first quarter of 2026 and commissioning of the wind farm scheduled for 2027.
The two wind farms of 50 units each, will have a total capacity of 1.44 GW and will be in the Polish exclusive economic zone of the Baltic Sea, at about 37 and 22 km from the coastline at the level of Łeba.