Wind Energy – Nordseecluser Projecs
Havfram and RWE have signed a contract for the transportation and installation of turbines for RWE’s Nordseecluster projects.

The projects combine four wind farm sites in the eastern part of the German North Sea and will have a total capacity of up to 1.6 GW.
Havfram Wind is to transport and support the installation of 104 Vestas offshore wind turbines with a capacity of 15 megawatts each, which are to be installed throughout two construction phases.
Both of Havfram Wind’s newbuild state-of-the-art Wind Turbine Installation Vessels will be utilised throughout both phases. Turbine installation of the two wind farms in Phase A is expected to start in 2026, and offshore construction works for Phase B are scheduled to begin in 2028.
Nordseecluster is expected to supply green electricity to the equivalent of 1,600,000 German households every year as of 2029.