General – Thor Platform
The construction of the Offshore High Voltage Station (OHVS) project officially commenced with a ‘steel cutting’ ceremony held at the HSM Offshore Energy, the Netherlands.
The ceremony took place end of November.
HSM Offshore Energy, together with its key subcontractors Iv-Offshore & Energy and GE Renewable Energy, was awared the engineering, procurement, construction, installation and commissioning of the offshore high voltage substation and its jacket foundation for the Thor platform in 2022.
With a planned capacity of over 1,000 MW, Thor will become Denmark’s largest offshore wind farm to date.
Once fully operational, no later than the end of 2027, the wind farm will be capable of generating enough green electricity to supply the equivalent of more than a million Danish households.