Wind Energy – Taiwan
According to a LinkedIn post of Dennis Sanou, CEO Changfang Xidao Offshore Wind Farms at Copenhagen Offshore Partners, all 62 three-legged jacket foundations have been installed at the 589 MW Changfang and Xidao wind farms offshore Taiwan,
![](https://ocean-energyresources.com/wp-content/uploads/2023/07/sanou-768x1024.jpeg)
Boskalis was in charge of installing the units at the offshore construction site, located some 15 kilometres off the coast of Changhua County.
The company deployed its Bokalift 1 and Bokalift 2 crane vessels for this mission. The ships were supported by vessels BOKA Atlantic and BOKA Tiamat which provided essential supporting activities.
The foundation installation was completed about 1 month ahead of schedule.