Wind Energy – Taiwan
According to a LinkedIn post of Dennis Sanou, CEO Changfang Xidao Offshore Wind Farms at Copenhagen Offshore Partners, all 62 three-legged jacket foundations have been installed at the 589 MW Changfang and Xidao wind farms offshore Taiwan,
Boskalis was in charge of installing the units at the offshore construction site, located some 15 kilometres off the coast of Changhua County.
The company deployed its Bokalift 1 and Bokalift 2 crane vessels for this mission. The ships were supported by vessels BOKA Atlantic and BOKA Tiamat which provided essential supporting activities.
The foundation installation was completed about 1 month ahead of schedule.