Wind Energy – Transition Pieces for Calvados
On Friday June 26, the last transition piece for the Calvados offshore wind farm in France sailed out from our location in Aalborg to marshalling destination in Vlissingen, Holland.
With the load out of the last 8 of a total of 64 foundations, Bladt has completed the scope of work for the project.
“It has been a pleasure for Bladt, which was subcontracted by Saipem, EPCI Contractor, to conduct this complex project, working closely with the Saipem project Team and other Contractors and Sub-Contractors involved, in an open and professional spirit,” said Erik Barrington, Senior Project Manager, Bladt Industries.
Each transition piece has a height of 24 meters and a weight of approximately 550 tons. Fabrication and loadout of all 64 transition pieces took place at Bladt Industries’ production facilities in Aalborg, Denmark.
The Calvados offshore wind farm will consist of 64 wind turbines with a total capacity of 450 MW and will be located more than 10 km off the French coast in water depths ranging from 22 to 31 meters.