General – Electrification
ONE-Dyas has awarded N-Sea a contract to install a subsea power cable between the Riffgat offshore wind farm and the new to be built N05-A gas production platform.
The scope of work comprises survey, design, supply, engineering, transport, installation, burial, termination and testing of the subsea cable asset with a route length of approx. 10km.
The preparations have already started in order for ONE-Dyas to deliver first gas by August 2024.
The subsea cable will allow the N05-A platform to operate by electrical power from the Riffgat offshore wind farm.