The Swedish government finally gave the green light for Vattenfall to lay cables on the seabed for the large Krieger Flak wind farm.
The project with the large wind farm out in the sea three miles south of Trelleborg was already started in 2002.
Twenty years later, in 2022, the Swedish government gave a building permit for the park. But then there was still a lack of permission from the government for the company to lay cables along the seabed to connect the park to the main grid.
Now Climate and Environment Minister Romina Pourmokhtari announced that the government is giving the green light for the underwater cables.