Ocean Energy Resources

GLOBAL NEWS SERVICE FOR THE FOSSIL AND RENEWABLE ENERGY COMMUNITIES

  • HOME
  • ADVERTISE WITH US
  • FREE SUBSCRIPTIONS
    • Digital Newsletter
  • MUST READ ARTICLES
  • CONTACT

BW Energy spuds first Hibiscus production well

Monday, January 9 2023

Fossil Energy – Gabon

BW Energy has started drilling the first production well on the Hibiscus / Ruche Phase 1 development in the Dussafu Block offshore Gabon.

Drilling operations began in line with the target of producing the first oil in March 2023.

The Borr Norve jack up arrived on location in late December and immediately started preparations for the drilling campaign. The first production well, DHIBM-3H, targets the Gamba sandstone reservoir on the Hibiscus field and is expected to take just over two months to drill and complete. Installation of flexible pipelines and risers, completing the 20-kilometre connection between the BW MaBoMo production facility and the FPSO BW Adolo, was also finalised last week.

The initial Hibiscus / Ruche Phase 1 drilling campaign targets the Hibiscus and Ruche fields which are expected to add approximately 30,000 barrels per day of total oil production when all wells are completed in early 2024.

Related posts:

  1. BW Energy achieves first oil from Hibiscus
  2. New 3-year contracts for 5 jack-up drilling rigs in Mexico
  3. New contract for jack-up Gunnlod
  4. Substantial oil discovery made in Hibiscus South prospect

Filed Under: Borr Drilling, BW Energy, Drilling, drilling rig, Gabon, Hibiscus, International News Tagged With: Borr Norve, BW Energy, Gabon, Hibiscus

All rights reserved - 2025 cookies