Wind Energy – HKZ
For the Hollandse Kust Zuid (HKZ) wind farm, Jumbo vessel Fairplayer completed the transport and installation (T&I) of secondary steel for 106 pre-installed monopiles.
Seaway 7, as the main contractor for the T&I of 140 foundations and a 66 kV in-array cable system, contracted Jumbo Offshore to install secondary steel for 106 of the 140 foundations.
By 06 September 2022 all 106 foundations were safely installed.