Iberdrola has completed the planning approval process for the 476 MW Baltic Eagle offshore wind farm.

The Spanish company received a positive decision from Germany’s Federal Maritime and Hydrographic Agency (BSH).
Following the approval from BSH, Iberdrola is now moving forward with the construction phase of the company’s second wind farm project in the German Baltic Sea after the 350 MW Wikinger.
Once the construction phase begins, all central components will be installed on site in 2023, with commissioning scheduled for 2024, Iberdrola said.