Ziton has been selected to overhaul and upgrade all blades at the German Meerwind site.
The campaign is in continuation of a similar project at West of Duddon Sands so as to build on lessons learned and retain experienced staff. This is in line with Ziton’s strategic focus on blade work and confirms the necessity for such services.
The blades will be upgraded in an onshore factory in Port of Esbjerg allowing for easy vessel access.
The engaged vessel spread will include the service jack-up Wind Server and a Service Operation Vessel (SOV) thereby optimizing working windows for the offshore technicians.
Preparations are well underway and the campaign will kick off in the near future and is expected to have a duration of 9-12 months weather depending.