The Dutch company Multimetaal Offshore successfully performed a challenging piping project for One-Dyas U.K on the Sean Papa platform.
This LLP compression project has the intention to extend the lifetime of the Sean P. platform.
Multimetaal started the project in February 2020 and finished the project after a period of ten months.
Part of this project was the installation of a second Siemens centrifugal compressor. This extra compressor stage has to compensate the decreasing well-pressures.
Multimetaal also installed a new suction scrubber, a liquid vessel, a production skimmer tank and a lot of duplex and carbon steel piping up to 18″.
This piping included more than 450 flange connections and a couple of welded tie-ins which were 100% NDE tested.