Wind Energy – He Dreiht
Sif, in joint venture with Smulders, will manufacture 64 Transition Pieces for the He Dreiht offshore wind project.
Production of all TP’s is scheduled for first half of 2023. Total weight of the 64 TP’s is 36.3 Kton.
The grid capacity of the He Dreiht offshore wind farm is 900 MW, operating 64 Vestas 15 MW turbines.
The Wind Farm is located within the German Exclusive Economic Zone (EEZ) of the North Sea, about 90 kilometers north of the Borkum Island and 110 kilometers west of the Helgoland Island.
Full commissioning of the wind farm is expected in the second half of 2025.
“We are pleased to have two experienced partners on board for our first subsidy-free offshore wind farm in the North Sea,” says Jörn Däinghaus, Project Director for EnBW He Dreiht. “The expansion of renewable energies is an important focus of EnBW’s strategy. It contributes to having at least half of our generation portfolio made up of renewable energies by the end of 2025 and paves the way for the company’s climate neutrality in 2035.”