Wind energy – HKZ
Muehlhan Wind Service (MWS) has signed an EPC contract with Siemens Gamesa for mechanical and electrical pre-assembly work for the Hollandse Kust Zuid (HKZ) offshore wind farm.
The contract includes complete mechanical and electrical pre-assembly work for 140 Siemens Gamesa 11 MW wind turbines, including all crane and lifting operations as well as ground transportation of nacelles, blades and towers for each phase of the project.
The pre-assembly work, which will take place at the Port of Rotterdam, is scheduled to begin in January 2022.