Wind energy – Taiwan
Hai Long Offshore Wind Project has awarded a consortium consisting of Semco Maritime and PTSC M&C a Preferred Supplier Agreement for two offshore substations for the Hai Long 2 and Hai Long 3 projects, off the Taiwanese coast.
The contract represents the largest offshore substations contract awarded in a Taiwanese project to date. It is also the consortium’s first and considered an important strategic breakthrough.
Semco Maritime will lead the consortium with PTSC M&C and cooperate closely with ISC Consulting Engineers as the primary sub-contractor on the project for Hai Long Offshore Wind Project.
The consortium and ISC Consulting Engineers will execute the project from Q4 2021 with offshore installation planned in 2024 and completion of commissioning in 2026.
The contract includes design, engineering, procurement, construction and commissioning of the two offshore substations including jackets, which will be manufactured at PTSC M&C’s yard facilities in Vungtau, a port city in South Vietnam.