Noreco a partner in DUC, The Danish Underground Consortium, announced that due to COVID-19, local governmental imposed restrictions at the fabrication yards have impacted the schedule of the new Tyra topsides, including through the global supply chain delivering key components for the topsides.
As a direct consequence of this impact, the installation of the four new topsides is rescheduled from 2021 to a 2022 installation-window.
The first production from the redeveloped Tyra is then expected in Q2 2023.
The Tyra field is the largest gas condensate field in the Danish sector of the North Sea.