Heerema’s SSCV Sleipnir has safely and sustainably completed its second project in the wind sector this season, having earlier executed the HKZ installation.
The work included the transportation and installation of two jackets for client Ørsted that will provide the foundation for the Hornsea 2 wind farm’s RCS and OSS platforms.
Sleipnir travelled to the OSS location on September 29 and installed the 5000 metric ton OSS jacket after transferring the 1500 metric ton RCS jacket and piles to the Sleipnir deck. After moving to the shallow water RCS location, Sleipnir installed the RCS Jacket.