Van Oord will be responsible for the installation of 62 three-legged jacket foundations in the St. Brieuc Offshore Wind Farm wind farm site, located around 20 km off the coast of France.
The photo shows one of the base plates of the template, which was ordered by Van Oord from Breman Machinery.
The template is 2.13 m high and the weight is approximately 32 tons. This mud-mat is currently being assembled at the Ijmuiden location of Breman.