Global Offshore has announced the completion of the export power cable installation at the Kincardine Floating Offshore Wind Farm pilot site in Scotland for Grupo Cobra.
The installation of the 18km export cable was completed by the Global Offshore team on board the highly versatile Global Symphony and marks the completion and connection of the first turbine, of six, on the 50MW Kincardine site. The overall project involved pre-installation surveys, grapnel work, installation, including the use of a dynamic riser to allow for movement of the platform, and trenching of the 18km export cable from Cove to the floating turbine, located just off the coast of Aberdeen.